Shreepati Group was established in the year 1984. This Company is into real estate development which focusses only on Cluster Redevelopment of the Brown field Projects located in South Mumbai and extended towards suburbs. We are largely based out in South Mumbai and we are the largest Cluster Redevelopment of Mumbai in India.
Redevelopment means purchasing the old dilapidated properties thereby amalgamating the nearby properties to form a cluster. Then vacating the tenant from their old premises is initiated and paying them if they wish to sell their old premises or shifting them in transit accommodation or paying them monthly rents till the possession is given in the newly developed building at our own cost. We are keen on enhancing their lifestyles by transforming their old 100 to 200 sq.ft. flats into new 500 to 600 sq.ft. apartments in the newly re-developed building.
The Cluster Redevelopment Policy known as DCPR 33(9) is a government policy which enables Bigger homes to the existing tenants.
It also has a provision to convert a non-residential tenement into a residential tenement.
We ensure to use High grade of concrete and steel during the construction of RCC Structure and Mivan Technology.
We provide Fire Fighting Systems, Concealed Electrical Fittings, Vitrified Tiles Flooring, Jaquar Sanitary Fittings, Astral Plumbing Fittings, Anodised Aluminium Windows, OTIS & Schindler make Escalators and FRD Doors as per CFO norms in the Rehab building to the tenants.
We provide amenities like Terrace Level Garden, Fitness Centre, Yoga Centre and Kidszone along with recreational garden (RG)
as per MOEF in the rehab building.
We also provide complete list of amenities, car parkings including surface and mechanical robotic along with the residential apartment thereby providing better standard of living in the Sale Building.
We build separate buildings for Sale as well as Rehab in the same property thereby enhancing better standard of living.

Stages Of Approvals:

The properties can either be cessed or non-cessed which may belong to MHADA, BMC, Collector or Private Co-operative housing societies.

To obtain No-objection Certificate (NOC), we submit plans to the concerned authority, then proceed with the approval process and acquire NOC’s.

In 33(9) scheme, the proposal is put up to the Nodal Officer, then the detailed report is put up for approval of Hon. Municipal Comissioner to schedule High Power Committee (HPC).

The approval is then sent to Urban development in Mantralay for obtaining Government Approval.

Then the proposal is processed for Letter of Intent (LOI).

Once the above process is completed, we start the application of Intimation of Disapproval (IOD) & Commencement Certificate (CC).

Once we start demolishing the structures onsite and the compliances of Intimation of Disapproval (IOD) is done, then the plinth CC is issued for the respective Project from BMC.

Once the building is in construction stage, we apply for further CC.